R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 06/12/2021
     District : Adilabad   


S.No. Mandal Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2021-2022 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Adilabad 2436 45.87 121.72 112.06 0 0 0 0 0 10 2436 46.64 67.71 87.14 2436 46.64 67.71 87.14 46.64 154.85 606
2 Bazarhathnoor 973 17.38 43.92 44.76 0 0 0 0 0 23 973 19.1 29.4 39.82 973 19.1 29.4 39.82 19.1 69.22 351
3 Bela 1954 50.99 83.1 89.88 0 0 0 0 0 147 1954 41.57 45.43 78.29 1954 41.57 45.43 78.29 41.57 123.72 369
4 Bheempoor 1105 23.87 48.43 50.83 0 0 0 0 0 49 1105 23.31 28.78 44.01 1105 23.31 28.78 44.01 23.31 72.79 507
5 Boath 1677 37.17 71.12 77.14 0 0 0 0 0 36 1677 39.33 41.29 66.73 1677 39.33 41.29 66.73 39.33 108.02 444
6 Gadiguda 563 15.4 23.67 25.9 0 0 0 0 0 37 563 14.15 12.82 21.28 563 14.15 12.82 21.28 14.15 34.09 56
7 Gudihathnur 1756 38.77 79.56 80.78 0 0 0 0 0 27 1756 39.31 45.9 67.07 1756 39.31 45.9 67.07 39.31 112.97 768
8 Ichoda 1694 35.25 78.24 77.92 0 0 0 0 0 55 1694 38.47 46.53 75.54 1694 38.47 46.53 75.54 38.47 122.06 856
9 Inderavelly 1425 31.45 66.79 65.55 0 0 0 0 0 70 1425 31.65 33.77 53.55 1425 31.65 33.77 53.55 31.65 87.32 260
10 Jainad 1807 45.53 70.06 83.12 0 0 0 0 0 21 1807 43.44 45.67 76.09 1807 43.44 45.67 76.09 43.44 121.76 997
11 Jainoor 1105 23.87 48.43 50.83 0 0 0 0 0 49 1105 23.31 28.78 44.01 1105 23.31 28.78 44.01 23.31 72.79 507
12 Jannaram 694 14.45 33.77 31.92 0 0 0 0 0 44 694 15.33 18.57 27 694 15.33 18.57 27 15.33 45.57 110
13 Kerameri 563 15.4 23.67 25.9 0 0 0 0 0 37 563 14.15 12.82 21.28 563 14.15 12.82 21.28 14.15 34.09 56
14 Mavala 435 11.57 16.5 20.01 0 0 0 0 0 1 435 10.13 8.96 17.78 435 10.13 8.96 17.78 10.13 26.75 163
15 Narnoor 1112 27.4 60.78 51.15 0 0 0 0 0 106 1112 24.29 25.17 38.86 1112 24.29 25.17 38.86 24.29 64.03 204
16 Neradigonda 1108 24.78 48.63 50.97 0 0 0 0 0 56 1108 24.65 29.65 44.33 1108 24.65 29.65 44.33 24.65 73.98 188
17 Sirikonda 694 14.45 33.77 31.92 0 0 0 0 0 44 694 15.33 18.57 27 694 15.33 18.57 27 15.33 45.57 110
18 Sirpur (U) 435 11.57 16.5 20.01 0 0 0 0 0 1 435 10.13 8.96 17.78 435 10.13 8.96 17.78 10.13 26.75 163
19 Talamadugu 2171 52.69 92.99 99.87 2 0.04 0.07 0 0 30 2169 44.28 49.73 79.03 2171 44.32 49.79 79.03 44.32 128.82 1091
20 Tamsi 954 22.78 35.97 43.88 0 0 0 0 0 38 954 19.66 22.01 40 954 19.66 22.01 40 19.66 62.01 500
21 Utnur 1756 40.31 80.85 80.78 0 0 0 0 0 131 1756 36.74 42.9 74.11 1756 36.74 42.9 74.11 36.74 117.01 308
Total 26417 600.94 1178.49 1215.18 2 0.04 0.07 0 0 1012 26415 574.97 663.4 1040.7 26417 575.01 663.47 1040.7 575.01 1704.17 8614
Note: Please click here to view Logic behind the report.
Last Updated: 05/12/2021 09:46 PM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)