R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 10/02/2025
     District : Hanumakonda         Mandal : Inole   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2024-2025 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Garimillapalle 73 2.09 2.7 3.36 0 0 0 0 0 0 73 2 2.02 1.15 73 2 2.02 1.15 2 3.17 35
2 Inole 187 4.98 6.9 8.6 0 0 0 0 0 0 187 4.68 3.45 3.82 187 4.68 3.45 3.82 4.68 7.27 134
3 Kakkiralapalle 96 2.65 3.32 4.42 0 0 0 0 0 0 96 2.4 1.28 2.24 96 2.4 1.28 2.24 2.4 3.51 61
4 Kondaparthy 99 2.61 4.34 4.55 0 0 0 0 0 0 98 2.24 3.25 1.49 98 2.24 3.25 1.49 2.24 4.74 70
5 Lingamarigudem 12 0.29 0.52 0.55 0 0 0 0 0 0 12 0.33 0.25 0.28 12 0.33 0.25 0.28 0.33 0.52 9
6 Mulkalagudem 5 0.15 0.27 0.23 0 0 0 0 0 0 5 0.19 0.16 0.09 5 0.19 0.16 0.09 0.19 0.25 3
7 Nandanam 134 3.39 4.84 6.16 0 0 0 0 0 0 134 3.08 1.78 3.17 134 3.08 1.78 3.17 3.08 4.95 120
8 Narsimulagudem 4 0.12 0.21 0.18 0 0 0 0 0 0 4 0.09 0.34 0 4 0.09 0.34 0 0.09 0.34 0
9 Ontimamidipalle 63 1.73 2.23 2.9 0 0 0 0 0 0 63 1.56 1.01 1.38 63 1.56 1.01 1.38 1.56 2.39 44
10 Panthini 106 3.08 3.88 4.88 0 0 0 0 0 0 106 2.88 1.52 2.44 106 2.88 1.52 2.44 2.88 3.96 69
11 Peramadlagudem 58 1.56 2 2.67 0 0 0 0 0 0 58 1.78 1.31 1.06 58 1.78 1.31 1.06 1.78 2.36 46
12 Punnelu 146 3.77 5.04 6.72 0 0 0 0 0 0 146 3.44 2.19 3.21 146 3.44 2.19 3.21 3.44 5.4 123
13 Reddipalem 74 2 2.77 3.4 0 0 0 0 0 0 74 2.05 1.65 1.38 74 2.05 1.65 1.38 2.05 3.03 63
14 Uduthagudem 12 0.28 0.44 0.55 0 0 0 0 0 0 12 0.29 0.44 0.18 12 0.29 0.44 0.18 0.29 0.62 6
15 Vanamalakanaparthi 47 1.3 1.92 2.16 0 0 0 0 0 0 47 0.93 1.01 0.83 47 0.93 1.01 0.83 0.93 1.83 36
16 Venkatapur 59 1.64 2.59 2.71 0 0 0 0 0 0 59 1.64 0.73 1.06 59 1.64 0.73 1.06 1.64 1.79 26
Total 1175 31.63 43.97 54.05 0 0 0 0 0 0 1174 29.56 22.38 23.77 1174 29.56 22.38 23.77 29.56 46.15 845
Note: Please click here to view Logic behind the report.
Last Updated: 09/02/2025 12:21 AM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)