R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 18/01/2022
     District : Hanumakonda         Mandal : Velair   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2021-2022 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Errabelli 99 2.3 3.28 4.55 0 0 0 0 0 0 99 2.8 1.81 4.55 99 2.8 1.81 4.55 2.8 6.36 18
2 Gundlasagar 49 1.32 2.49 2.25 0 0 0 0 0 0 49 1.24 2.16 0.95 49 1.24 2.16 0.95 1.24 3.11 13
3 Kammaripeta 89 2.63 3.71 4.09 0 0 0 0 0 0 89 2.63 2.53 3.45 89 2.63 2.53 3.45 2.63 5.98 34
4 Kannaram 169 4.61 6.33 7.77 0 0 0 0 0 0 169 6.58 2.55 6.67 169 6.58 2.55 6.67 6.58 9.22 42
5 Maddelagudem 45 1.2 2.02 2.07 0 0 0 0 0 0 45 1.18 2.38 1.2 45 1.18 2.38 1.2 1.18 3.58 22
6 Mallikudurla 99 2.81 4.05 4.55 0 0 0 0 0 0 99 2.85 3.62 3.68 99 2.85 3.62 3.68 2.85 7.3 48
7 Peechara 106 3 4.46 4.88 0 0 0 0 0 0 106 3 2.71 3.36 106 3 2.71 3.36 3 6.07 51
8 Shalapalli 129 3.31 6.15 5.93 0 0 0 0 0 0 129 3.26 5.72 4.14 129 3.26 5.72 4.14 3.26 9.87 39
9 Sodeshapalle 62 1.82 2.96 2.85 0 0 0 0 0 1 62 1.76 2.64 1.15 62 1.76 2.64 1.15 1.76 3.79 16
10 Velair 148 4.23 6.58 6.81 0 0 0 0 0 0 148 4.33 5.17 4.69 148 4.33 5.17 4.69 4.33 9.86 43
Total 995 27.23 42.04 45.77 0 0 0 0 0 1 995 29.65 31.3 33.84 995 29.65 31.3 33.84 29.65 65.14 326
Note: Please click here to view Logic behind the report.
Last Updated: 17/01/2022 09:51 PM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)