R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 11/02/2025
     District : Bhadradri Kothagudem         Mandal : Tekulapalle   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2024-2025 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Bhiludu Thanda 51 1.45 2.5 2.35 0 0 0 0 0 0 51 1.02 0.6 1.2 51 1.02 0.6 1.2 1.02 1.79 1
2 Boddu Thanda H/O Betham 183 4.31 7.46 8.42 0 0 0 0 0 0 183 3.44 3.88 3.36 183 3.44 3.88 3.36 3.44 7.23 0
3 Chandruthanda 28 0.75 1.43 1.29 0 0 0 0 0 0 28 0.58 0.03 0.74 28 0.58 0.03 0.74 0.58 0.77 0
4 Chintalalanka 66 1.62 2.81 3.04 0 0 0 0 0 0 66 1.04 0.81 1.52 66 1.04 0.81 1.52 1.04 2.33 4
5 Chinthonichelka 2 0.06 0.11 0.09 0 0 0 0 0 0 2 0.03 0.02 0.05 2 0.03 0.02 0.05 0.03 0.07 0
6 Gangaram 1 0 0.08 0.05 0 0 0 0 0 0 1 0 -.05 0.05 1 0 -.05 0.05 0 0 0
7 Gollapalle 106 2.77 5.04 4.88 0 0 0 0 0 0 106 1.94 1.35 2.39 106 1.94 1.35 2.39 1.94 3.74 10
8 Kistaram 15 0.42 0.83 0.69 0 0 0 0 0 0 15 0.45 0.58 0.18 15 0.45 0.58 0.18 0.45 0.76 0
9 Kotha Thanda G 100 2.67 5.29 4.6 0 0 0 0 0 0 100 2 1.39 2.16 100 2 1.39 2.16 2 3.55 9
10 Koyagudem 230 5.43 8.4 10.58 0 0 0 0 0 0 230 4.13 3.23 4.88 230 4.13 3.23 4.88 4.13 8.1 0
11 Kuntalla 63 1.42 2.39 2.9 0 0 0 0 0 0 63 1.2 0.92 1.33 63 1.2 0.92 1.33 1.2 2.25 0
12 Madras Thanda 70 1.82 2.77 3.22 0 0 0 0 0 0 70 1.4 0.79 1.43 70 1.4 0.79 1.43 1.4 2.22 0
13 Mutyalampadu Xroads 64 1.56 2.62 2.94 0 0 0 0 0 0 64 1.01 0.4 1.61 64 1.01 0.4 1.61 1.01 2.01 5
14 Shambunivanigudem 28 0.79 1.48 1.29 0 0 0 0 0 0 28 0.51 0.83 0.46 28 0.51 0.83 0.46 0.51 1.29 0
15 Sukalibodu 27 0.67 1.06 1.24 0 0 0 0 0 0 27 0.54 0.59 0.46 27 0.54 0.59 0.46 0.54 1.05 0
16 Sulanagar 90 1.99 3.27 4.14 0 0 0 0 0 0 90 1.34 1.78 1.79 90 1.34 1.78 1.79 1.34 3.57 1
Total 1124 27.73 47.53 51.7 0 0 0 0 0 0 1124 20.62 17.14 23.6 1124 20.62 17.14 23.6 20.62 40.74 30
Note: Please click here to view Logic behind the report.
Last Updated: 10/02/2025 09:48 PM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)