R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 14/02/2025
     District : Nagarkurnool         Mandal : Kodair   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2024-2025 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Badigadinne 31 0.89 1.19 1.43 0 0 0 0 0 0 31 0.87 0.13 0.78 31 0.87 0.13 0.78 0.87 0.91 23
2 Bawaipalle 62 1.36 2.84 2.85 0 0 0 0 0 0 62 1.42 0.96 1.39 62 1.42 0.96 1.39 1.42 2.35 39
3 Janumpalle 28 0.58 1.43 1.29 0 0 0 0 0 0 28 0.65 0.68 0.51 28 0.65 0.68 0.51 0.65 1.18 16
4 Kodair 88 2.34 3.6 4.05 0 0 0 0 0 0 88 2.23 1 1.98 88 2.23 1 1.98 2.23 2.98 63
5 Kondraopalle 77 2 3.69 3.54 0 0 0 0 0 0 77 2.14 1.4 1.43 77 2.14 1.4 1.43 2.14 2.82 26
6 Machupalle 14 0.39 0.56 0.64 0 0 0 0 0 0 14 0.37 0.17 0.28 14 0.37 0.17 0.28 0.37 0.45 11
7 Mailaram 12 0.36 0.44 0.55 0 0 0 0 0 0 12 0.35 -.02 0.28 12 0.35 -.02 0.28 0.35 0.25 10
8 Muthireddipallee 11 0.3 0.42 0.51 0 0 0 0 0 0 11 0.3 0.19 0.23 11 0.3 0.19 0.23 0.3 0.42 7
9 Nagulapalle 48 1.28 2.25 2.21 0 0 0 0 0 0 48 1.28 0.47 0.87 48 1.28 0.47 0.87 1.28 1.34 15
10 Narsaipally 63 1.49 2.77 2.9 0 0 0 0 0 0 63 1.6 0.53 1.61 63 1.6 0.53 1.61 1.6 2.14 34
11 Paspula 33 0.92 1.51 1.52 0 0 0 0 0 0 33 0.89 0.28 0.69 33 0.89 0.28 0.69 0.89 0.97 14
12 Rajapuram 22 0.52 1.1 1.01 0 0 0 0 0 0 22 0.53 0.89 0.18 22 0.53 0.89 0.18 0.53 1.07 13
13 Singaipalle 9 0.27 0.36 0.41 0 0 0 0 0 0 9 0.27 0.28 0.14 9 0.27 0.28 0.14 0.27 0.42 5
14 Teegalapalle 105 2.43 4.8 4.83 0 0 0 0 0 0 105 2.73 1.27 2.39 105 2.73 1.27 2.39 2.73 3.67 62
15 Yetham 3 0.09 0.17 0.14 0 0 0 0 0 0 3 0.11 0.14 0 3 0.11 0.14 0 0.11 0.14 0
Total 606 15.2 27.13 27.88 0 0 0 0 0 0 606 15.75 8.35 12.75 606 15.75 8.35 12.75 15.75 21.1 338
Note: Please click here to view Logic behind the report.
Last Updated: 13/02/2025 12:35 AM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)