R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 18/01/2022
     District : Peddapalli         Mandal : Mutharam Manthani   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2021-2022 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Adivi Srirampoor 147 3.28 5.05 6.76 0 0 0 0 0 1 147 3.4 2.79 6.69 147 3.4 2.79 6.69 3.4 9.49 20
2 Dharyapur 9 0.22 0.33 0.41 0 0 0 0 0 0 9 0.26 0.13 0.41 9 0.26 0.13 0.41 0.26 0.55 2
3 Haripuram 16 0.41 0.58 0.74 0 0 0 0 0 0 16 0.41 0.31 0.74 16 0.41 0.31 0.74 0.41 1.05 4
4 Ippalapally 54 1.29 1.91 2.48 0 0 0 0 0 0 54 1.35 0.9 2.12 54 1.35 0.9 2.12 1.35 3.02 7
5 Keshanpalle 83 2.03 2.94 3.82 0 0 0 0 0 0 83 2.19 1.45 3.71 83 2.19 1.45 3.71 2.19 5.16 8
6 Khammampally 253 5.77 8.8 11.64 0 0 0 0 0 1 253 6.08 5.83 11.12 253 6.08 5.83 11.12 6.08 16.95 30
7 Lakkaram 110 2.53 3.76 5.06 0 0 0 0 0 0 110 2.84 1.85 5.06 110 2.84 1.85 5.06 2.84 6.91 33
8 Machupeta 67 1.48 2.37 3.08 0 0 0 0 0 0 67 1.71 1.15 3.02 67 1.71 1.15 3.02 1.71 4.17 16
9 Mutharam 143 3.29 5.24 6.58 0 0 0 0 0 0 143 3.41 2.81 6.24 143 3.41 2.81 6.24 3.41 9.05 9
10 Mydambanda 47 1.27 1.82 2.16 0 0 0 0 0 0 47 1.69 0.86 1.93 47 1.69 0.86 1.93 1.69 2.78 25
11 Odedu 165 3.89 5.82 7.59 0 0 0 0 0 0 165 4.27 3.14 7.13 165 4.27 3.14 7.13 4.27 10.27 21
12 Parupalle 58 1.32 2.27 2.67 0 0 0 0 0 0 58 1.49 1.25 2.44 58 1.49 1.25 2.44 1.49 3.69 4
13 Potharam 49 1.19 1.9 2.25 0 0 0 0 0 0 49 1.34 1.01 2.02 49 1.34 1.01 2.02 1.34 3.03 9
14 Seethampet 40 0.89 1.41 1.84 0 0 0 0 0 0 40 0.86 0.87 1.66 40 0.86 0.87 1.66 0.86 2.53 4
Total 1241 28.85 44.18 57.09 0 0 0 0 0 2 1241 31.3 24.36 54.28 1241 31.3 24.36 54.28 31.3 78.63 192
Note: Please click here to view Logic behind the report.
Last Updated: 17/01/2022 09:51 PM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)