R13.20 Nirmal Bharat Abhiyan Project - Work Status Report (EGS + RWS Funding)
Report for the Work : Individual House Hold Latrine (GO No250)
Report as on Date : 18/01/2022
     District : Wanaparthy         Mandal : Srirangapur   


S.No. Panchayat Name Administratively Sanctioned In Progress-Expenditure Details No. of IHHLs Completed during the month No. of IHHLs Completed in Finyear 2021-2022 Completed-Expenditure Details Total Expenditure No.of Photos Uploaded
No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) No. of Works EGS Funding (in Lakhs) NBA Funding (in Lakhs) Total(EGS+NBA) (in Lakhs)
Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material Material Unskilled Material
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Janampeta 12 0.2 0.57 0.55 0 0 0 0 0 0 12 0.25 0.4 0.55 12 0.25 0.4 0.55 0.25 0.95 10
2 Kamballapur 42 1.01 1.68 1.93 0 0 0 0 0 0 42 1.02 1.21 1.93 42 1.02 1.21 1.93 1.02 3.14 41
3 Seripalle 12 0.36 0.42 0.55 0 0 0 0 0 0 12 0.36 0.26 0.51 12 0.36 0.26 0.51 0.36 0.77 9
4 Srirangapur 26 0.66 1.13 1.2 0 0 0 0 0 0 26 0.68 0.62 1.06 26 0.68 0.62 1.06 0.68 1.68 17
5 Thatipamula 38 1.05 1.58 1.75 0 0 0 0 0 0 38 0.95 1.1 1.2 38 0.95 1.1 1.2 0.95 2.29 24
6 Venkatapur 8 0.15 0.44 0.37 0 0 0 0 0 0 8 0.18 0.23 0.32 8 0.18 0.23 0.32 0.18 0.55 7
Total 138 3.43 5.81 6.35 0 0 0 0 0 0 138 3.44 3.81 5.57 138 3.44 3.81 5.57 3.44 9.38 108
Note: Please click here to view Logic behind the report.
Last Updated: 17/01/2022 09:51 PM
  Note:- No. of Inprogress Works are shown as per physical status (Irrespective of the RWS Expenditure done)